AC Hotel by Marriott Atlanta International Airport College Park,Georgia

Phase One - Marriott AC Hotel

our ‘Phase One’ development of a Marriott AC Hotel has successfully raised funds for EB-5 investment and the construction will be completed by December 2019.

After Seccessful Capital Raise and ground breaking of Phase-I,Inviting Investors of EB5 Capital raise for Phase-II Sheraton

Previous Week

Current Week

Work Items Completed

Site Work :

  • Manhole brickwork installed
  • Water line to pump room installed

Bulding Level1 / In – Ground :

  • Electrical rough-in and waste line installation continuing

Bulding Level 2 :

  • CMU exterior wall installed
  • HVAC, electrical, and plumbing ceiling rough-ins completed

Mockup Rooms (206 & 208) :

  • Marriott rough-in review completed successfully
  • Framing complete on four different room types
  • Electrical and LV wall rough-in complete (no wiring pulled)
  • Plumbing stub-out in walls complete
  • All wall blocking installed
  • All FF&E outlined on the floor
  • Ceiling lighting marked on the floor reflecting overhead locations

Bulding Level 5-A :

  • Concrete formwork completed
  • Rebar, PT cables, and embeds laid-out and installed
  • HVAC block-outs, electrical rough-in, and plumbing sleeves laid-out and installed
  • Elevated slab placed and finished
  • Column rebar cages installed
  • PT cables stressed

Bulding Level 5-B :

  • Concrete formwork installed
  • Rebar, PT cables, and embeds laid-out, and plumbing sleeves laid-out and installed
  • HVAC block-outs, electrical rough-in, and plumbing sleeves laid-out and installed.

Work Items Progress

Building Level 6-A :

  • Concrete formwork completion
  • Rebar, PT cables, and embeds lay-out and installation
  • HVAC block-outs, electrical rough-in, and plumbing sleeves lay-out and installation
  • Elevated slab placement and finishing
  • Column rebar cages installation
  • Columns cast-in-place
  • PT cables stressed

Bulding Level 6-B :

  • Concrete formwork completion
  • Rebar, PT cables, and embeds lay-out and installation
  • HVAC block-outs, electrical rough-in, and plumbing sleeves lay-out and installation

Work Items for Next Week

Bulding Level1 / In – Ground :

  • Electrical Rough-Ins and waste line installation

Bulding Level 3-B :

  • CMU Exterior wall completed

Bulding Level 7-A :

  • Concrete form deck : complete installation
  • Rebar and PT cables : layout and installation
  • HVAC, electrical rough-in, plumbing block-outs, and plumbing sleeves : layout and installation
  • Embeds : layout and install at Stair 1
  • Concrete deck : place and finish
  • Concrete columns : rebar cage installation

Bulding Level 7-B :

  • Concrete form deck : complete installation
  • Rebar and PT cables : layout and installation
  • HVAC, electrical rough-in, plumbing block-outs, and plumbing sleeves : layout and installation
  • Embeds : layout and install at Stair 1
  • Concrete deck : place and finish
  • Concrete columns : rebar cage installation